The compressed natural gas station assembly, ordered by Slovenian partner NRG trgovina in zastopanje, d.o.o., was completed on February 22, 2021. It was then transported from Macel Plin d.o.o.’s production hall to its final location in Ljubljana, Letališka cesta, for installation by end-user Energetika Ljubljana d.o.o.
This delivery marked Macel Plin d.o.o.’s first compressed natural gas station to receive an assembly certificate—the CE mark of the product issued by the Notified Body. This advancement improves the company’s production of compressed natural gas stations, aligning it with European norms and standards for the European market.
Investor: NRG trgovina in zastopanje d.o.o., Tehnološki park 19, 1000 Ljubljana, Slovenia
Subject of the Contract: Equipment of CNG plant by Letaliska cesta
Introduction to work: 16.12.2020.
Planned commissioning: spring 2021.
Project location: Letališka cesta, Ljubljana, Slovenia
Capacity: The estimated capacity of the CNG station is 1300 Nm3 / h of gas, with an inlet pressure of 16 bar g.
The CNG station contains the following:
- an electrical control room,
- an inlet pipeline connected to the local gas system,
- a compressor skid with associated equipment,
- a gas dryer,
- a compressed gas storage room with 25 cylinders at a working pressure of 275 bar.